United States › Grid › Interconnection queues › Arkansas
SOLAR · MISOSolar project J1125, Cross County
Solar project J1125, Cross County is a 135 MW solar request under construction in the MISO interconnection queue, in Cross County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusUnder construction
- PlanningQueued Mar 2018 (completed)
- ConsentedAug 2020 (completed)
- Construction (current stage)
- OperatingTarget Mar 2023 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1125
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- Wynne South - Wynne East AECC 161 kV Line Tap
- Location
- Cross County, Arkansas
- Technology
- Solar: 135 MW
- Total requested
- 135 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Under Construction
- Queue status
- Active
- Entered queue
- 12 March 2018
- Agreement signed
- 12 August 2020
- Proposed online date
- March 2023
Location
Marker shows the centre of Cross County; the queue data does not give exact sites.
Other requests in Cross County
- Onshore wind project J2577, Cross CountyOnshore wind · 200 MW · in study
- Solar project J1816, Cross CountySolar · 135 MW · in study
- Onshore wind project J1842, Cross CountyOnshore wind · 135 MW · in study
- Solar project J3570, Cross CountySolar · 300 MW · withdrawn
- Solar project J1857, Cross CountySolar · 250 MW · withdrawn
- Solar project J3783, Cross CountySolar · 200 MW · withdrawn
- Solar + storage project J3606, Cross CountySolar + storage · 198 MW · withdrawn
- Solar + storage project J3510, Cross CountySolar + storage · 175 MW · withdrawn
- Solar + storage project J3458, Cross CountySolar + storage · 170 MW · withdrawn
- Solar project J4036, Cross CountySolar · 160 MW · withdrawn
- Onshore wind project J3814, Cross CountyOnshore wind · 135 MW · withdrawn
- Solar project J1267, Cross CountySolar · 135 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem