United States › Grid › Interconnection queues › Arkansas
ONSHORE WIND · MISOOnshore wind project J2577, Cross County
Onshore wind project J2577, Cross County is a 200 MW onshore wind request in interconnection study in the MISO interconnection queue, in Cross County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2577
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- Parkin
- Location
- Cross County, Arkansas
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- October 2025
Location
Marker shows the centre of Cross County; the queue data does not give exact sites.
Other requests in Cross County
- Solar project J1125, Cross CountySolar · 135 MW · under construction
- Solar project J1816, Cross CountySolar · 135 MW · in study
- Onshore wind project J1842, Cross CountyOnshore wind · 135 MW · in study
- Solar project J3570, Cross CountySolar · 300 MW · withdrawn
- Solar project J1857, Cross CountySolar · 250 MW · withdrawn
- Solar project J3783, Cross CountySolar · 200 MW · withdrawn
- Solar + storage project J3606, Cross CountySolar + storage · 198 MW · withdrawn
- Solar + storage project J3510, Cross CountySolar + storage · 175 MW · withdrawn
- Solar + storage project J3458, Cross CountySolar + storage · 170 MW · withdrawn
- Solar project J4036, Cross CountySolar · 160 MW · withdrawn
- Onshore wind project J3814, Cross CountyOnshore wind · 135 MW · withdrawn
- Solar project J1267, Cross CountySolar · 135 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem