United States › Grid › Interconnection queues › Arkansas

SOLAR · MISO

Solar project J1816, Cross County

Solar project J1816, Cross County is a 135 MW solar request in interconnection study in the MISO interconnection queue, in Cross County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusIn planning
  1. PlanningQueued Mar 2022 (current stage)
  2. ConsentedMay 2023 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1816
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
FISHER - CHERRY VALLEY 161.0kV
Location
Cross County, Arkansas
Technology
Solar: 135 MW
Total requested
135 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
17 March 2022
Agreement signed
11 May 2023
Proposed online date
November 2025

Location

Marker shows the centre of Cross County; the queue data does not give exact sites.

Power plants in Arkansas · Transmission lines in Arkansas

Other requests in Cross County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem