United States › Grid › Interconnection queues › Arkansas

ONSHORE WIND · MISO

Onshore wind project J1842, Cross County

Onshore wind project J1842, Cross County is a 135 MW onshore wind request in interconnection study in the MISO interconnection queue, in Cross County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusIn planning
  1. PlanningQueued Oct 2021 (current stage)
  2. ConsentedDec 2024 (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J1842
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
FORREST CITY N SS - WYNNE SOUTH 161.0kV
Location
Cross County, Arkansas
Technology
Wind: 135 MW
Total requested
135 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA In Process; Post GIA Status: Not Started
Queue status
Active
Entered queue
19 October 2021
Agreement signed
26 December 2024
Proposed online date
October 2024

Location

Marker shows the centre of Cross County; the queue data does not give exact sites.

Power plants in Arkansas · Transmission lines in Arkansas

Other requests in Cross County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem