United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Interconnection queue in MISO (Midcontinent)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,646350.1 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,646 requests ยท page 1 of 33
ProjectCapacityStatusLocationRegionQueuedOnline
Schahfer CCGTs
Gas ยท NIPSCO
2,740 MWIn study Jasper, INMISO Aug 2025target 2028
Gas project J3996, St. Charles County
Gas
2,220 MWIn study St. Charles, MOMISO Apr 2025target 2030
Richland Parish generators
Gas ยท Entergy Louisiana, LLC
1,640 MWIn study Richland Parish, LAMISO Aug 2025target 2028
Richland Parish generators
Gas ยท Entergy Louisiana, LLC
1,640 MWIn study Richland Parish, LAMISO Aug 2025target 2028
Franklin Farms
Gas ยท Entergy Louisiana, LLC
1,640 MWIn study Richland Parish, LAMISO Aug 2025target 2028
Gas project J3999, Vermillion County
Gas
1,540 MWIn study Vermillion, INMISO Apr 2025target 2030
Gas project J4071, Livingston Parish County
Gas
1,500 MWIn study Livingston Parish, LAMISO Oct 2025target 2030
Gas project J4024, Monroe County
Gas
1,499 MWIn study Monroe, MIMISO May 2025target 2030
Gas project J4025, Monroe County
Gas
1,499 MWIn study Monroe, MIMISO May 2025target 2030
Gas project J3799, Livingston County
Gas
1,452 MWIn study Livingston, MIMISO Apr 2024target 2030
Gas project J3922, Branch County
Gas
1,445 MWIn study Branch, MIMISO Mar 2025target 2030
Gas project J3923, Washtenaw County
Gas
1,414 MWIn study Washtenaw, MIMISO Feb 2025target 2030
Gas project J4113, Cerro Gordo County
Gas
1,315 MWIn study Cerro Gordo, IAMISO Oct 2025target 2028
Gas project J3935, Genesee County
Gas
1,268 MWIn study Genesee, MIMISO Feb 2025target 2030
Replacing 464.5 MW Steam/Gas with 97.8 MW Steam; DOW Chem
Gas
1,232 MWIn study Iberville, LAMISO May 2024target 2025
Red Oak Ridge Energy Center
Gas ยท Invenergy
1,211 MWIn study Kenosha, WIMISO Aug 2025target 2027
Gas project E0016, Calumet County
Gas ยท Invenergy
1,211 MWIn study Calumet, WIMISO Aug 2025target 2027
Gas project J4164, Dane County
Gas
1,203 MWIn study Dane, WIMISO Sep 2025target 2030
Gas project J4165, Kenosha County
Gas
1,203 MWIn study Kenosha, WIMISO Sep 2025target 2030
Gas project J4014, Calumet County
Gas
1,203 MWIn study Calumet, WIMISO May 2025target 2030
Replace 1163.3 MW of Sabine Units 3, 4 & 1 with 2 on 1 Combined Cycle Gas Turbine facility; Sabine 1
Gas
1,166 MWIn study Orange, TXMISO Aug 2020target 2026
Gas project J955, Sangamon County
Gas
1,165 MWUnder construction Sangamon, ILMISO Mar 2018target 2025
Gas project J3941, Deuel County
Gas
1,144 MWIn study Deuel, SDMISO Mar 2025target 2030
Replacement; Oak Creek Units 5-8
Gas
1,138 MWIn study Milwaukee, WIMISO Jun 2024target 2027
Malden CCGT
Gas ยท NIPSCO
1,090 MWIn study Porter, INMISO Aug 2025target 2028
Replacing 1014.7 MW of coal generation with Gas/Steam; Cayuga CC1 CC2
Gas
1,040 MWIn study Vermillion, INMISO Feb 2024target 2028
Gas project J1813, Desoto County
Gas
1,005 MWIn study Desoto, MSMISO Jul 2022target 2002
Solar project J4161, Watonwan County
Solar
1,000 MWIn study Watonwan, MNMISO Sep 2025target 2030
Other project J1490, Randolph County
Other
1,000 MWAgreement signed Randolph, MOMISO Apr 2019target 2024
Gas project E0050, Linn County
Gas ยท Interstate Power and Light Company (IPL)
987 MWIn study Linn, IAMISO Nov 2025target 2028
Gas project J4116, Walworth County
Gas
950 MWIn study Walworth, WIMISO Oct 2025target 2030
Replacing 864 MW of coal with Natural Gas Generators; Castle Bluff
Gas
824 MWIn study St. Louis, MOMISO May 2024target 2025
Solar project J2186, Fulton County
Solar
821 MWIn study Fulton, ILMISO Jun 2022target 2024
Lakeover CCCT
Gas ยท Entergy Mississippi, LLC
820 MWIn study Hinds, MSMISO Aug 2025target 2028
Gas project E0030, Jefferson County
Gas ยท Entergy Texas, Inc.
820 MWIn study Jefferson, TXMISO Aug 2025target 2027
Vicksburg CCCT
Gas ยท Entergy Mississippi, LLC
820 MWIn study Warren, MSMISO Aug 2025target 2027
Gas project J4138, Iberville Parish County
Gas
805 MWIn study Iberville Parish, LAMISO Oct 2025target 2030
Gas project J4191, Iberville Parish County
Gas
805 MWIn study Iberville Parish, LAMISO Oct 2025target 2030
Gas project E0049, Cerro Gordo County
Gas ยท Interstate Power and Light Company (IPL)
798 MWIn study Cerro Gordo, IAMISO Oct 2025target 2028
Gas project E0010, Marshall County
Gas ยท Interstate Power and Light Company (IPL)
798 MWIn study Marshall, IAMISO Aug 2025target 2028
Gas project E0048, Rapides Parish County
Gas ยท Cleco Power LLC
775 MWIn study Rapides Parish, LAMISO Sep 2025target 2028
Entergy Louisiana LRZ 9 Generation Resource
Gas ยท Entergy Louisiana, LLC
770 MWIn study Calcasieu Parish, LAMISO Aug 2025target 2028
Gas project J3829, Hot Spring County
Gas
770 MWIn study Hot Spring, ARMISO Apr 2024target 2028
Gas project J3874, Union County
Gas
770 MWIn study Union, ARMISO Dec 2024target 2028
Gas project J4133, De Soto Parish County
Gas
756 MWIn study De Soto Parish, LAMISO Oct 2025target 2030
Replacing 749 MW of coal generation with BESS; Campbell 3
Other
749 MWIn study Ottawa, MIMISO Nov 2023target 2028
Nuclear project J4040, Van Buren County
Nuclear
735 MWIn study Van Buren, MIMISO Jul 2025target 2030
Replacing 722 MW Coal with 285 MW of Battery and 437MW of Gas; Schahfer
Gas
733 MWIn study Jasper, INMISO Dec 2024target 2027
Gas project J1246, Iberville Parish County
Gas
725 MWAgreement signed Iberville Parish, LAMISO Apr 2019target 2025
Gas project J351, St. Joseph County
Gas
715 MWAgreement signed St. Joseph, INMISO May 2014target 2020
Page 1 of 33

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)