United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in ISO-NE (New England)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown7214.6 GW
Active in queue14.6 GW72 requests
Agreement signed8,609 MW45 requests
Withdrawn982118.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

72 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
SouthCoast Wind 1
Offshore wind
1,200 MWAgreement signed MAISO-NE Apr 2021target 2031
Bay State Wind 4 Offshore Wind
Offshore wind
1,200 MWAgreement signed MAISO-NE Dec 2019target 2033
Offshore Wind
Offshore wind
827 MWIn study MAISO-NE Dec 2018target 2032
Vineyard Offshore Wind
Offshore wind
800 MWAgreement signed MAISO-NE Nov 2016target 2026
Park City Offshore Wind
Offshore wind
791 MWAgreement signed MAISO-NE Dec 2017target 2029
Revoultion Offshore wind
Offshore wind
704 MWAgreement signed RIISO-NE Sep 2018target 2026
Battery Storage
Battery storage
508 MWAgreement signed Middlesex, MAISO-NE Jun 2021target 2028
Battery Storage
Battery storage
500 MWIn study Middlesex, MAISO-NE Jun 2024target 2028
Battery Storage
Battery storage
500 MWIn study Barnstable, MAISO-NE May 2024target 2028
Offshore Wind Inc. (Q806)
Offshore wind
487 MWIn study MAISO-NE Mar 2021target 2032
Battery Storage
Battery storage
350 MWIn study Bristol, MAISO-NE Oct 2023target 2027
Lite Brite Battery Storage
Battery storage
306 MWAgreement signed Suffolk, MAISO-NE Jul 2021target 2028
Willard Storage (NYISO-C24-148)
Battery storage
300 MWIn study Rensselaer, NYISO-NE Dec 2024target 2028
Battery Storage
Battery storage
300 MWIn study Norfolk, MAISO-NE Mar 2022target 2028
Battery Storage
Battery storage
300 MWIn study Worcester, MAISO-NE Apr 2024target 2028
Battery Storage
Battery storage
290 MWIn study Berkshire, MAISO-NE Apr 2024target 2028
Medway Grid Battery Storage
Battery storage
250 MWAgreement signed Norfolk, MAISO-NE Mar 2019target 2025
Battery Storage
Battery storage
250 MWIn study Hampden, MAISO-NE Mar 2023target 2029
Hecate Energy Eastern Ave Energy Center
Battery storage
250 MWAgreement signed Suffolk, MAISO-NE Apr 2021target 2026
Battery Storage
Battery storage
225 MWIn study Essex, MAISO-NE Jun 2024target 2028
Naugatuck Avenue Battery Storage
Battery storage
205 MWAgreement signed New Haven, CTISO-NE Jan 2021target 2027
Battery Storage
Battery storage
205 MWAgreement signed Washington, RIISO-NE Sep 2021target 2029
Norman Street Battery Storage
Battery storage
204 MWAgreement signed Middlesex, MAISO-NE Mar 2021target 2028
Battery Storage
Battery storage
204 MWAgreement signed Worcester, MAISO-NE Oct 2022target 2027
Battery Storage
Battery storage
200 MWIn study Essex, MAISO-NE Jun 2024target 2028
Battery Storage
Battery storage
180 MWIn study Worcester, MAISO-NE May 2024target 2028
Solar
Solar
180 MWIn study York, MEISO-NE Jul 2023target 2029
Green Apple Solar
Solar
179 MWAgreement signed Androscoggin, MEISO-NE Feb 2021target 2027
Battery Storage
Battery storage
170 MWIn study Berkshire, MAISO-NE May 2024target 2029
Battery Storage
Battery storage
170 MWIn study Hampden, MAISO-NE May 2024target 2029
Energy Storage
Battery storage
170 MWAgreement signed Norfolk, MAISO-NE Apr 2019target 2027
Battery Storage
Battery storage
168 MWIn study Bristol, MAISO-NE Jun 2023target 2027
Solar
Solar
165 MWAgreement signed Somerset, MEISO-NE Feb 2021target 2029
Battery Storage Addition (to QP1086)
Solar + storage
160 MWAgreement signed Knox, MEISO-NE May 2022target 2026
NY Chateaugay 0 Willis Rd Storage (NYISO-C24-304-004)
Battery storage
150 MWIn study Franklin, NYISO-NE Dec 2024target 2028
Solar
Solar
150 MWAgreement signed Hartford, CTISO-NE Mar 2022target 2028
Battery Storage
Battery storage
142 MWAgreement signed Litchfield, CTISO-NE Oct 2022target 2029
Battery Storage
Battery storage
136 MWIn study Berkshire, MAISO-NE Apr 2024target 2028
Battery Storage
Battery storage
125 MWIn study Middlesex, MAISO-NE Jun 2024target 2028
Broadleaf Solar
Solar
101 MWAgreement signed Hartford, CTISO-NE Nov 2021target 2027
Three Rivers Solar
Solar
100 MWAgreement signed Hancock, MEISO-NE Jan 2019target 2026
Solar
Solar
100 MWIn study Rockingham, NHISO-NE Jul 2023target 2028
Warren Meadow Solar
Solar
74.5 MWAgreement signed Knox, MEISO-NE Nov 2020target 2026
Ocean State Power uprate
Gas
73.2 MWAgreement signed Providence, RIISO-NE Apr 2018target 2026
Bear Swamp Unit 1 and 2 Upgrade
Battery storage
66.0 MWAgreement signed Berkshire, MAISO-NE Jan 2016target 2023
Husky Solar
Solar
50.2 MWAgreement signed Windham, CTISO-NE Jun 2021target 2029
FPS Panton Solar
Solar
50.0 MWAgreement signed Addison, VTISO-NE Dec 2018target 2027
West Springfield 45 MW BESS
Battery storage
45.0 MWAgreement signed Hampden, MAISO-NE Jun 2022target 2029
Solar Knox
Solar
33.5 MWAgreement signed Knox, MEISO-NE Oct 2021target 2027
Solar
Solar
25.0 MWIn study Hartford, CTISO-NE Apr 2022target 2027
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)