United States › Grid › Interconnection queues › Massachusetts

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 508 MW battery storage request with a signed interconnection agreement in the ISO-NE interconnection queue, in Middlesex County, Massachusetts.

Queue statusConsented
  1. PlanningQueued Jun 2021 (completed)
  2. ConsentedApr 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1143
Grid region
ISO-NE (New England)
Connection point (POI)
Mystic 345 kV between breaker 101, 106 and 107
Location
Middlesex County, Massachusetts
Technology
Battery: 508 MW
Total requested
508 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
15 June 2021
Agreement signed
4 April 2024
Proposed online date
May 2028

Location

Marker shows the centre of Middlesex County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Middlesex County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem