Kendall Reconfiguration Project

Kendall Reconfiguration Project is a 1.9 MW gas request built and operating in the ISO-NE interconnection queue, in Middlesex County, Massachusetts.

Queue statusOperating
  1. PlanningQueued Jan 2015 (completed)
  2. ConsentedMay 2016 (completed)
  3. Construction (completed)
  4. OperatingTarget May 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
490
Grid region
ISO-NE (New England)
Connection point (POI)
Where line 875-539 interconnects with TO''s 115 kv bus at station 875
Location
Middlesex County, Massachusetts
Technology
Gas: 1.9 MW · Oil
Total requested
1.9 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
15 January 2015
Agreement signed
31 May 2016
Proposed online date
May 2016

Location

Marker shows the centre of Middlesex County; the queue data does not give exact sites.