United States › Grid › Interconnection queues › Connecticut
SOLAR · ISO-NEBroadleaf Solar
Broadleaf Solar is a 101 MW solar request with a signed interconnection agreement in the ISO-NE interconnection queue, in Hartford County, Connecticut.
Queue statusConsented
- PlanningQueued Nov 2021 (completed)
- ConsentedFeb 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Oct 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1192
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- N. Bloomfield to Agawam 345kV Line. POI is approximately 3.6 mi north of N. Bloomfield (345kV) and 11.5 mi south of Agawam (345kV).
- Location
- Hartford County, Connecticut
- Technology
- Solar: 101 MW
- Total requested
- 101 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 4 November 2021
- Agreement signed
- 27 February 2025
- Proposed online date
- October 2027
Location
No county location in the queue data.
Power plants in Connecticut · Transmission lines in Connecticut
Other requests in Hartford County
- SolarSolar · 150 MW · agreement signed
- SolarSolar · 25.0 MW · in study
- Solar IncreaseSolar · 5.0 MW · in study
- Gravel Pit SolarSolar · 50.0 MW · built
- Algonquin Power Windsor Locks Cogeneration FacilitGas · 47.5 MW · built
- Gravel Pit Solar IncreaseSolar · 45.0 MW · built
- SolarSolar · 26.4 MW · built
- Gravel Pit Solar increaseSolar · 25.0 MW · built
- NB Fuel CellGas · 20.2 MW · built
- Nutmeg Solar, LLCSolar · 19.9 MW · built
- Hamilton SundstrandGas · 5.0 MW · built
- Battery StorageBattery storage · 326 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem