SOLAR Β· ISO-NE

Solar

Solar is a 26.4 MW solar request built and operating in the ISO-NE interconnection queue, in Hartford County, Connecticut, connecting to NU.

Queue statusOperating
  1. PlanningQueued Feb 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
713
Grid region
ISO-NE (New England)
Utility / transmission owner
NU
Connection point (POI)
Eversource North Simsbury
Location
Hartford County, Connecticut
Technology
Solar: 26.4 MW
Total requested
26.4 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
21 February 2018
Proposed online date
December 2019

Location

No county location in the queue data.