United States › Grid › Interconnection queues › Connecticut
GAS · ISO-NEAlgonquin Power Windsor Locks Cogeneration Facilit
Algonquin Power Windsor Locks Cogeneration Facilit is a 47.5 MW gas request built and operating in the ISO-NE interconnection queue, in Hartford County, Connecticut.
Request details
- Queue ID
- 318
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- CL&P Windsor Locks Substation
- Location
- Hartford County, Connecticut
- Technology
- Gas: 47.5 MW · Oil
- Total requested
- 47.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 24 November 2009
- Proposed online date
- April 2010
Location
No county location in the queue data.
Power plants in Connecticut · Transmission lines in Connecticut
Other requests in Hartford County
- SolarSolar · 150 MW · agreement signed
- Broadleaf SolarSolar · 101 MW · agreement signed
- SolarSolar · 25.0 MW · in study
- Solar IncreaseSolar · 5.0 MW · in study
- Gravel Pit SolarSolar · 50.0 MW · built
- Gravel Pit Solar IncreaseSolar · 45.0 MW · built
- SolarSolar · 26.4 MW · built
- Gravel Pit Solar increaseSolar · 25.0 MW · built
- NB Fuel CellGas · 20.2 MW · built
- Nutmeg Solar, LLCSolar · 19.9 MW · built
- Hamilton SundstrandGas · 5.0 MW · built
- Battery StorageBattery storage · 326 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem