🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Connecticut

SOLAR · ISO-NE

Gravel Pit Solar increase

Gravel Pit Solar increase is a 25.0 MW solar request built and operating in the ISO-NE interconnection queue, in Hartford County, Connecticut.

Queue statusOperating
  1. PlanningQueued Dec 2019 (completed)
  2. ConsentedApr 2021 (completed)
  3. Construction (completed)
  4. OperatingTarget Mar 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
940
Grid region
ISO-NE (New England)
Connection point (POI)
Line cut and three-breaker ring bus of the 115 kV Connecticut Light & Power Company line between Barbour Hill and Windsor Locks.
Location
Hartford County, Connecticut
Technology
Solar: 25.0 MW
Total requested
25.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
4 December 2019
Agreement signed
20 April 2021
Proposed online date
March 2024

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Hartford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem