BATTERY STORAGE · ISO-NE

West Springfield 45 MW BESS

West Springfield 45 MW BESS is a 45.0 MW battery storage request with a signed interconnection agreement in the ISO-NE interconnection queue, in Hampden County, Massachusetts.

Queue statusConsented
  1. PlanningQueued Jun 2022 (completed)
  2. ConsentedOct 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1272
Grid region
ISO-NE (New England)
Connection point (POI)
West Springfield Station, 115kV Bus (existing 8C-3X 140 MVA transformer; position WS#2).
Location
Hampden County, Massachusetts
Technology
Battery: 45.0 MW
Total requested
45.0 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Active
Entered queue
8 June 2022
Agreement signed
16 October 2024
Proposed online date
May 2029

Location

Marker shows the centre of Hampden County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Hampden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem