CC Administrative Increase

CC Administrative Increase is a 550 MW gas request withdrawn in the ISO-NE interconnection queue, in Hampden County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2011 (completed)
  2. Withdrawn / abandonedSep 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
373
Grid region
ISO-NE (New England)
Connection point (POI)
WMECO Ludlow 19S substation
Location
Hampden County, Massachusetts
Technology
Gas: 550 MW · Oil
Total requested
550 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
12 August 2011
Withdrawn
September 2012

Location

Marker shows the centre of Hampden County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Hampden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem