United States › Grid › Interconnection queues › Massachusetts

SOLAR · ISO-NE

Belchertown Substation - NG Western MA Area Cluster Study

Belchertown Substation - NG Western MA Area Cluster Study is a 8.0 MW solar request built and operating in the ISO-NE interconnection queue, in Hampden County, Massachusetts, connecting to NGRID.

Queue statusOperating
  1. PlanningQueued Dec 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Aug 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
809
Grid region
ISO-NE (New England)
Utility / transmission owner
NGRID
Connection point (POI)
NG Belchertown Substation
Location
Hampden County, Massachusetts
Technology
Solar: 8.0 MW
Total requested
8.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
14 December 2018
Proposed online date
August 2021

Location

Marker shows the centre of Hampden County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Hampden County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem