United States › Grid › Interconnection queues › Maine
SOLAR + STORAGE · ISO-NEBattery Storage Addition (to QP1086)
Battery Storage Addition (to QP1086) is a 160 MW solar + storage request with a signed interconnection agreement in the ISO-NE interconnection queue, in Knox County, Maine.
Queue statusConsented
- PlanningQueued May 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Nov 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1261
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- CMP 115kV line Section 80
- Location
- Knox County, Maine
- Technology
- Solar: 160 MW · Battery
- Total requested
- 160 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 17 May 2022
- Proposed online date
- November 2026
Location
Marker shows the centre of Knox County; the queue data does not give exact sites.
Other requests in Knox County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem