SOLAR + STORAGE · ISO-NE

Battery Storage Addition (to QP1086)

Battery Storage Addition (to QP1086) is a 160 MW solar + storage request with a signed interconnection agreement in the ISO-NE interconnection queue, in Knox County, Maine.

Queue statusConsented
  1. PlanningQueued May 2022 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1261
Grid region
ISO-NE (New England)
Connection point (POI)
CMP 115kV line Section 80
Location
Knox County, Maine
Technology
Solar: 160 MW · Battery
Total requested
160 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Active
Entered queue
17 May 2022
Proposed online date
November 2026

Location

Marker shows the centre of Knox County; the queue data does not give exact sites.

Power plants in Maine · Transmission lines in Maine

Other requests in Knox County