United States βΊ Grid βΊ Interconnection queues βΊ Maine
SOLAR + STORAGE Β· ISO-NESolar and Battery
Solar and Battery is a 5.0 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Knox County, Maine.
Queue statusWithdrawn / abandoned
- PlanningQueued Aug 2019 (completed)
- Withdrawn / abandonedOct 2019 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 919
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- CMP Thomaston Creek substation - Circuit 246D1
- Location
- Knox County, Maine
- Technology
- Solar: 5.0 MW Β· Battery
- Total requested
- 5.0 MW
- Queue status
- Withdrawn
- Entered queue
- 29 August 2019
- Proposed online date
- December 2020
- Withdrawn
- October 2019
Location
Marker shows the centre of Knox County; the queue data does not give exact sites.
Other requests in Knox County
- Battery Storage Addition (to QP1086)Solar + storage Β· 160 MW Β· agreement signed
- Warren Meadow SolarSolar Β· 74.5 MW Β· agreement signed
- Solar KnoxSolar Β· 33.5 MW Β· agreement signed
- SolarSolar Β· 31.4 MW Β· withdrawn
- SolarSolar Β· 20.0 MW Β· withdrawn
- Highland/Park St 115 kV SS - Midcoast Area DG StudySolar Β· 2.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem