United States › Grid › Interconnection queues › Maine
SOLAR · ISO-NEHighland/Park St 115 kV SS - Midcoast Area DG Study
Highland/Park St 115 kV SS - Midcoast Area DG Study is a 2.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Knox County, Maine, connecting to CMP.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2023 (completed)
- Withdrawn / abandonedJan 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1455
- Grid region
- ISO-NE (New England)
- Utility / transmission owner
- CMP
- Connection point (POI)
- CMP Highland/Park St 115 kV Substation
- Location
- Knox County, Maine
- Technology
- Solar: 2.0 MW
- Total requested
- 2.0 MW
- Queue status
- Withdrawn
- Entered queue
- 2 October 2023
- Proposed online date
- December 2024
- Withdrawn
- January 2025
Location
Marker shows the centre of Knox County; the queue data does not give exact sites.
Other requests in Knox County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem