Three Rivers Solar

Three Rivers Solar is a 100 MW solar request with a signed interconnection agreement in the ISO-NE interconnection queue, in Hancock County, Maine.

Queue statusConsented
  1. PlanningQueued Jan 2019 (completed)
  2. ConsentedOct 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
833
Grid region
ISO-NE (New England)
Connection point (POI)
New 115 kV breaker Ring bus, tapping 115 kV Line 93 (Emera Maine) between Bull Hill & Deblois
Location
Hancock County, Maine
Technology
Solar: 100 MW
Total requested
100 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Active
Entered queue
9 January 2019
Agreement signed
24 October 2023
Proposed online date
December 2026

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.