United States βΊ Grid βΊ Interconnection queues βΊ Maine
ONSHORE WIND Β· ISO-NEWind
Wind is a 250 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Hancock County, Maine.
Queue statusWithdrawn / abandoned
- PlanningQueued Dec 2014 (completed)
- Withdrawn / abandonedJun 2018 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 486
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Rebel Hill 115 kV
- Location
- Hancock County, Maine
- Technology
- Wind: 250 MW
- Total requested
- 250 MW
- Service type
- Energy only (ERIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 19 December 2014
- Proposed online date
- December 2021
- Withdrawn
- June 2018
Location
Marker shows the centre of Hancock County; the queue data does not give exact sites.
Other requests in Hancock County
- Three Rivers SolarSolar Β· 100 MW Β· agreement signed
- Weaver WindOnshore wind Β· 72.6 MW Β· built
- Hancock Wind ProjectOnshore wind Β· 51.0 MW Β· built
- Bull Hill Wind Phase IOnshore wind Β· 34.5 MW Β· built
- Bucksport G5Other Β· 25.0 MW Β· built
- Solar Increase (QP1145)Solar Β· 54.1 MW Β· withdrawn
- SolarSolar Β· 51.4 MW Β· withdrawn
- SolarSolar Β· 20.7 MW Β· withdrawn
- BiomassOther Β· 18.1 MW Β· withdrawn
- SolarSolar Β· 1.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem