πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

SOLAR Β· ISO-NE

Solar

Solar is a 51.4 MW solar request withdrawn in the ISO-NE interconnection queue, in Hancock County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2021 (completed)
  2. Withdrawn / abandonedApr 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1098
Grid region
ISO-NE (New England)
Connection point (POI)
34.5 kV bus at Versant Power Trenton substation at 44°26'19.81"N, 68°22'29.11"W
Location
Hancock County, Maine
Technology
Solar: 51.4 MW
Total requested
51.4 MW
Service type
Network resource (NRIS)
Study phase
Not Started
Queue status
Withdrawn
Entered queue
19 February 2021
Proposed online date
December 2024
Withdrawn
April 2024

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Hancock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem