ONSHORE WIND · ISO-NE

Bull Hill Wind Phase I

Bull Hill Wind Phase I is a 34.5 MW onshore wind request built and operating in the ISO-NE interconnection queue, in Hancock County, Maine.

Queue statusOperating
  1. PlanningQueued Nov 2009 (completed)
  2. ConsentedMar 2012 (completed)
  3. Construction (completed)
  4. OperatingTarget Oct 2012 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
317
Grid region
ISO-NE (New England)
Connection point (POI)
BHE Line 66
Location
Hancock County, Maine
Technology
Wind: 34.5 MW
Total requested
34.5 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Operational
Entered queue
4 November 2009
Agreement signed
31 March 2012
Proposed online date
October 2012

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.