United States βΊ Grid βΊ Interconnection queues βΊ Maine
OTHER Β· ISO-NEBiomass
Biomass is a 18.1 MW other request withdrawn in the ISO-NE interconnection queue, in Hancock County, Maine.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2010 (completed)
- Withdrawn / abandonedJun 2011 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 335
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- CMP 115 kV
- Location
- Hancock County, Maine
- Technology
- Other: 18.1 MW
- Total requested
- 18.1 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 14 May 2010
- Proposed online date
- March 2012
- Withdrawn
- June 2011
Location
Marker shows the centre of Hancock County; the queue data does not give exact sites.
Other requests in Hancock County
- Three Rivers SolarSolar Β· 100 MW Β· agreement signed
- Weaver WindOnshore wind Β· 72.6 MW Β· built
- Hancock Wind ProjectOnshore wind Β· 51.0 MW Β· built
- Bull Hill Wind Phase IOnshore wind Β· 34.5 MW Β· built
- Bucksport G5Other Β· 25.0 MW Β· built
- WindOnshore wind Β· 250 MW Β· withdrawn
- Solar Increase (QP1145)Solar Β· 54.1 MW Β· withdrawn
- SolarSolar Β· 51.4 MW Β· withdrawn
- SolarSolar Β· 20.7 MW Β· withdrawn
- SolarSolar Β· 1.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem