SOLAR Β· ISO-NE

Solar Increase (QP1145)

Solar Increase (QP1145) is a 54.1 MW solar request withdrawn in the ISO-NE interconnection queue, in Hancock County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2022 (completed)
  2. Withdrawn / abandonedMay 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1299
Grid region
ISO-NE (New England)
Connection point (POI)
Versant 115kV Line 57 (new ring bus located 0.7 miles north of Versant's 115kV substation).
Location
Hancock County, Maine
Technology
Solar: 54.1 MW
Total requested
54.1 MW
Service type
Network resource (NRIS)
Study phase
In Progress
Queue status
Withdrawn
Entered queue
18 August 2022
Proposed online date
September 2026
Withdrawn
May 2025

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Hancock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem