SOLAR Β· ISO-NE

Solar

Solar is a 1.0 MW solar request withdrawn in the ISO-NE interconnection queue, in Hancock County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2021 (completed)
  2. Withdrawn / abandonedJun 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1165
Grid region
ISO-NE (New England)
Connection point (POI)
34.5kV Line on Bar Harbor Road. The 34.5 kV line from Ellsworth to Trenton is not explicitly modeled in the power flow. We added a model for this line and then tapped it at tap 30% of the total line
Location
Hancock County, Maine
Technology
Solar: 1.0 MW
Total requested
1.0 MW
Service type
Network resource (NRIS)
Study phase
In Progress
Queue status
Withdrawn
Entered queue
22 October 2021
Proposed online date
July 2023
Withdrawn
June 2025

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in Hancock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem