🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Massachusetts

BATTERY STORAGE · ISO-NE

Lite Brite Battery Storage

Lite Brite Battery Storage is a 306 MW battery storage request with a signed interconnection agreement in the ISO-NE interconnection queue, in Suffolk County, Massachusetts.

Queue statusConsented
  1. PlanningQueued Jul 2021 (completed)
  2. ConsentedAug 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1148
Grid region
ISO-NE (New England)
Connection point (POI)
Electric Avenue 115 kV substation (bus number 110926), Zone MA_NST
Location
Suffolk County, Massachusetts
Technology
Battery: 306 MW
Total requested
306 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
13 July 2021
Agreement signed
9 August 2024
Proposed online date
May 2028

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Suffolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem