OTHER · ISO-NEGas Turbine (Additional Capacity)
Gas Turbine (Additional Capacity) is a 29.0 MW other request withdrawn in the ISO-NE interconnection queue, in Suffolk County, Massachusetts.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2006 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 154
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- NSTAR Chelsea Substation
- Location
- Suffolk County, Massachusetts
- Technology
- Oil: 29.0 MW
- Total requested
- 29.0 MW
- Service type
- Other
- Queue status
- Withdrawn
- Entered queue
- 31 May 2006
- Proposed online date
- August 2008
Location
Marker shows the centre of Suffolk County; the queue data does not give exact sites.
Power plants in Massachusetts · Transmission lines in Massachusetts
Other requests in Suffolk County
- Lite Brite Battery StorageBattery storage · 306 MW · agreement signed
- Hecate Energy Eastern Ave Energy CenterBattery storage · 250 MW · agreement signed
- MATEP (Medical Area Total Energy Project)Gas · 42.0 MW · built
- MATEP -3rd CTGGas · 14.1 MW · built
- MATEP (Combined Cycle) IncreaseGas · 1.7 MW · built
- Combined CycleGas · 800 MW · withdrawn
- Combined CycleGas · 800 MW · withdrawn
- Battery StorageBattery storage · 700 MW · withdrawn
- Battery StorageBattery storage · 276 MW · withdrawn
- Gas TurbineOther · 168 MW · withdrawn
- MATEP - Third CTGGas · 12.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem