Gas Turbine

Gas Turbine is a 168 MW other request withdrawn in the ISO-NE interconnection queue, in Suffolk County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2006 (completed)
  2. Withdrawn / abandonedNov 2007 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
147
Grid region
ISO-NE (New England)
Connection point (POI)
NSTAR Chelsea Substation
Location
Suffolk County, Massachusetts
Technology
Oil: 168 MW
Total requested
168 MW
Service type
Other
Queue status
Withdrawn
Entered queue
28 February 2006
Proposed online date
June 2010
Withdrawn
November 2007

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in Massachusetts Β· Transmission lines in Massachusetts

Other requests in Suffolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem