United States › Grid › Interconnection queues › Massachusetts

GAS · ISO-NE

MATEP (Medical Area Total Energy Project)

MATEP (Medical Area Total Energy Project) is a 42.0 MW gas request built and operating in the ISO-NE interconnection queue, in Suffolk County, Massachusetts, connecting to NSTAR.

Queue statusOperating
  1. PlanningQueued May 2006 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. Operating (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
152
Grid region
ISO-NE (New England)
Utility / transmission owner
NSTAR
Connection point (POI)
NSTAR Brighton Substation
Location
Suffolk County, Massachusetts
Technology
Gas: 42.0 MW · Oil
Total requested
42.0 MW
Service type
Other
Study phase
IA Executed
Queue status
Operational
Entered queue
30 May 2006

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Suffolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem