πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Massachusetts

GAS Β· ISO-NE

Combined Cycle

Combined Cycle is a 800 MW gas request withdrawn in the ISO-NE interconnection queue, in Suffolk County, Massachusetts.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedAug 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1011
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource Mystic 345 kV station
Location
Suffolk County, Massachusetts
Technology
Gas: 800 MW
Total requested
800 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
20 April 2020
Proposed online date
June 2024
Withdrawn
August 2020

Location

Marker shows the centre of Suffolk County; the queue data does not give exact sites.

Power plants in Massachusetts Β· Transmission lines in Massachusetts

Other requests in Suffolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem