United States β€Ί Grid β€Ί Interconnection queues β€Ί Maine

SOLAR Β· ISO-NE

Solar

Solar is a 180 MW solar request in interconnection study in the ISO-NE interconnection queue, in York County, Maine.

Queue statusIn planning
  1. PlanningQueued Jul 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
1427
Grid region
ISO-NE (New England)
Connection point (POI)
Lebanon, Maine Line 391 Buxton Sub (CMP) to Scobie Pond (Eversource). GPS coordinates of the POI: 43°22'51.59"N, 70°55'57.74"W. ** This new tap is located approximately 27.8 miles southwest of Buxt
Location
York County, Maine
Technology
Solar: 180 MW
Total requested
180 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Active
Entered queue
21 July 2023
Proposed online date
December 2029

Location

Marker shows the centre of York County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in York County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem