Battery Storage is a 50.7 MW battery storage request withdrawn in the ISO-NE interconnection queue, in York County, Maine.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2022 (completed)
- Withdrawn / abandonedMay 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1250
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- CMP Goosefare 115kV Substation 43 31 22 N 70 26 59 W
- Location
- York County, Maine
- Technology
- Battery: 50.7 MW
- Total requested
- 50.7 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 14 April 2022
- Proposed online date
- November 2024
- Withdrawn
- May 2023
Location
Marker shows the centre of York County; the queue data does not give exact sites.
Other requests in York County
- GDC Saco SolarSolar Β· 20.0 MW Β· agreement signed
- Emery Meadow SolarSolar Β· 16.4 MW Β· agreement signed
- SolarSolar Β· 180 MW Β· in study
- Sanford Airport SolarSolar Β· 50.0 MW Β· built
- Mousam River SolarSolar Β· 20.0 MW Β· built
- Westbrook Energy Center ExpansionGas Β· 9.5 MW Β· built
- Bonny Eagle Energy Storage - UprateOther Β· 8.0 MW Β· built
- SolarSolar Β· 4.8 MW Β· built
- Skelton Station Modernization Phase 1Hydro Β· 1.1 MW Β· built
- SolarSolar Β· 150 MW Β· withdrawn
- SolarSolar Β· 50.0 MW Β· withdrawn
- Sanford/Quaker Hill CMP Cluster 4Solar + storage Β· 21.2 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem