BATTERY STORAGE Β· ISO-NE

Battery Storage

Battery Storage is a 50.7 MW battery storage request withdrawn in the ISO-NE interconnection queue, in York County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2022 (completed)
  2. Withdrawn / abandonedMay 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1250
Grid region
ISO-NE (New England)
Connection point (POI)
CMP Goosefare 115kV Substation 43 31 22 N 70 26 59 W
Location
York County, Maine
Technology
Battery: 50.7 MW
Total requested
50.7 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
14 April 2022
Proposed online date
November 2024
Withdrawn
May 2023

Location

Marker shows the centre of York County; the queue data does not give exact sites.

Power plants in Maine Β· Transmission lines in Maine

Other requests in York County