United States › Grid › Interconnection queues › Maine
SOLAR · ISO-NEEmery Meadow Solar
Emery Meadow Solar is a 16.4 MW solar request with a signed interconnection agreement in the ISO-NE interconnection queue, in York County, Maine.
Queue statusConsented
- PlanningQueued Apr 2020 (completed)
- ConsentedJun 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Sep 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1021
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- CMP 34.5 kV, Section 182
- Location
- York County, Maine
- Technology
- Solar: 16.4 MW
- Total requested
- 16.4 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 27 April 2020
- Agreement signed
- 21 June 2024
- Proposed online date
- September 2027
Location
Marker shows the centre of York County; the queue data does not give exact sites.
Other requests in York County
- GDC Saco SolarSolar · 20.0 MW · agreement signed
- SolarSolar · 180 MW · in study
- Sanford Airport SolarSolar · 50.0 MW · built
- Mousam River SolarSolar · 20.0 MW · built
- Westbrook Energy Center ExpansionGas · 9.5 MW · built
- Bonny Eagle Energy Storage - UprateOther · 8.0 MW · built
- SolarSolar · 4.8 MW · built
- Skelton Station Modernization Phase 1Hydro · 1.1 MW · built
- SolarSolar · 150 MW · withdrawn
- Battery StorageBattery storage · 50.7 MW · withdrawn
- SolarSolar · 50.0 MW · withdrawn
- Sanford/Quaker Hill CMP Cluster 4Solar + storage · 21.2 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem