United States › Grid › Interconnection queues › Maine

SOLAR · ISO-NE

Emery Meadow Solar

Emery Meadow Solar is a 16.4 MW solar request with a signed interconnection agreement in the ISO-NE interconnection queue, in York County, Maine.

Queue statusConsented
  1. PlanningQueued Apr 2020 (completed)
  2. ConsentedJun 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1021
Grid region
ISO-NE (New England)
Connection point (POI)
CMP 34.5 kV, Section 182
Location
York County, Maine
Technology
Solar: 16.4 MW
Total requested
16.4 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
27 April 2020
Agreement signed
21 June 2024
Proposed online date
September 2027

Location

Marker shows the centre of York County; the queue data does not give exact sites.

Power plants in Maine · Transmission lines in Maine

Other requests in York County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem