Bear Swamp Unit 1 and 2 Upgrade

Bear Swamp Unit 1 and 2 Upgrade is a 66.0 MW battery storage request with a signed interconnection agreement in the ISO-NE interconnection queue, in Berkshire County, Massachusetts.

Queue statusConsented
  1. PlanningQueued Jan 2016 (completed)
  2. ConsentedApr 2018 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
592
Grid region
ISO-NE (New England)
Connection point (POI)
GRID 230 kV Bear Swamp substation
Location
Berkshire County, Massachusetts
Technology
Other Storage: 66.0 MW
Total requested
66.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
21 January 2016
Agreement signed
30 April 2018
Proposed online date
January 2023

Location

Marker shows the centre of Berkshire County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Berkshire County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem