BATTERY STORAGE · ISO-NE

Bear Swamp Pumping Load Increase

Bear Swamp Pumping Load Increase is a 333 MW battery storage request built and operating in the ISO-NE interconnection queue, in Berkshire County, Massachusetts.

Queue statusOperating
  1. PlanningQueued Nov 2021 (completed)
  2. ConsentedNov 2021 (completed)
  3. Construction (completed)
  4. OperatingTarget Nov 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
1194
Grid region
ISO-NE (New England)
Connection point (POI)
The existing POI of the Bear Swamp generating station
Location
Berkshire County, Massachusetts
Technology
Other Storage: 333 MW
Total requested
333 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Operational
Entered queue
9 November 2021
Agreement signed
10 November 2021
Proposed online date
November 2021

Location

Marker shows the centre of Berkshire County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Berkshire County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem