United States › Grid › Interconnection queues › Massachusetts
BATTERY STORAGE · ISO-NEEnergy Storage
Energy Storage is a 170 MW battery storage request with a signed interconnection agreement in the ISO-NE interconnection queue, in Norfolk County, Massachusetts.
Queue statusConsented
- PlanningQueued Apr 2019 (completed)
- ConsentedJan 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Jul 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 877
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- National Grid's South Wrentham 115kV substation
- Location
- Norfolk County, Massachusetts
- Technology
- Battery: 170 MW
- Total requested
- 170 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 11 April 2019
- Agreement signed
- 19 January 2024
- Proposed online date
- July 2027
Location
Marker shows the centre of Norfolk County; the queue data does not give exact sites.
Power plants in Massachusetts · Transmission lines in Massachusetts
Other requests in Norfolk County
- Medway Grid Battery StorageBattery storage · 250 MW · agreement signed
- NEA Bell. Uprate (Northeast Energy Associates, LP)Gas · 1.4 MW · agreement signed
- Battery StorageBattery storage · 300 MW · in study
- Medway Peaker - SEMARIGas · 208 MW · built
- Thomas A. Watson Generating StationGas · 108 MW · built
- Kearsarge Solar with batterySolar + storage · 5.4 MW · built
- Battery Storage Increase (QP1238)Battery storage · 301 MW · withdrawn
- Battery StorageBattery storage · 270 MW · withdrawn
- Battery StorageBattery storage · 254 MW · withdrawn
- Battery StorageBattery storage · 250 MW · withdrawn
- Gas TurbineGas · 208 MW · withdrawn
- Battery StorageBattery storage · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem