🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Massachusetts

SOLAR + STORAGE · ISO-NE

Kearsarge Solar with battery

Kearsarge Solar with battery is a 5.4 MW solar + storage request built and operating in the ISO-NE interconnection queue, in Norfolk County, Massachusetts, connecting to NGRID.

Queue statusOperating
  1. PlanningQueued Aug 2018 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
778
Grid region
ISO-NE (New England)
Utility / transmission owner
NGRID
Connection point (POI)
GRID circuit 335W1, Pole 11 on Williams Way, Bellingham
Location
Norfolk County, Massachusetts
Technology
Solar: 5.4 MW · Battery
Total requested
5.4 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
31 August 2018
Proposed online date
December 2021

Location

Marker shows the centre of Norfolk County; the queue data does not give exact sites.

Power plants in Massachusetts · Transmission lines in Massachusetts

Other requests in Norfolk County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem