Husky Solar is a 50.2 MW solar request with a signed interconnection agreement in the ISO-NE interconnection queue, in Windham County, Connecticut.

Queue statusConsented
  1. PlanningQueued Jun 2021 (completed)
  2. ConsentedOct 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1138
Grid region
ISO-NE (New England)
Connection point (POI)
The POI will be located about 6.9 miles from the 1607/1505 line ROW (Exeter Tap) and about 1.1 miles from the Exeter Sub 54N along the 115 kV underground line to the Exeter Sub 54N.
Location
Windham County, Connecticut
Technology
Solar: 50.2 MW
Total requested
50.2 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Active
Entered queue
3 June 2021
Agreement signed
16 October 2024
Proposed online date
May 2029

Location

No county location in the queue data.