🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Connecticut

HYDRO · ISO-NE

Mechanicsville Hydro Increase

Mechanicsville Hydro Increase is a 0.3 MW hydro request built and operating in the ISO-NE interconnection queue, in Windham County, Connecticut.

Queue statusOperating
  1. PlanningQueued Oct 2012 (completed)
  2. ConsentedMar 2013 (completed)
  3. Construction (completed)
  4. OperatingTarget Mar 2013 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
402
Grid region
ISO-NE (New England)
Connection point (POI)
CL&P 23 kV at Mechanicsville
Location
Windham County, Connecticut
Technology
Hydro: 0.3 MW
Total requested
0.3 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
16 October 2012
Agreement signed
1 March 2013
Proposed online date
March 2013

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Windham County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem