BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 200 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Windham County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2018 (completed)
  2. Withdrawn / abandonedMar 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
831
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource Killingly 345kV substation, Lat: 41.881266°, Long: -71.891253°
Location
Windham County, Connecticut
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
In Progress
Queue status
Withdrawn
Entered queue
21 December 2018
Proposed online date
May 2024
Withdrawn
March 2021

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Windham County