United States › Grid › Interconnection queues › Maine
SOLAR · ISO-NEGreen Apple Solar
Green Apple Solar is a 179 MW solar request with a signed interconnection agreement in the ISO-NE interconnection queue, in Androscoggin County, Maine.
Queue statusConsented
- PlanningQueued Feb 2021 (completed)
- ConsentedAug 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Nov 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1097
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- 44.172365, -70.104225 CMP 115kv Line 212
- Location
- Androscoggin County, Maine
- Technology
- Solar: 179 MW
- Total requested
- 179 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 15 February 2021
- Agreement signed
- 2 August 2024
- Proposed online date
- November 2027
Location
Marker shows the centre of Androscoggin County; the queue data does not give exact sites.
Other requests in Androscoggin County
- BD Solar Church HillSolar · 20.0 MW · agreement signed
- Turner Meadow SolarSolar · 19.8 MW · agreement signed
- Riley-Jay-Otis-LivermoreHydro · 28.3 MW · built
- SolarSolar · 20.0 MW · built
- Gulf Island Unit 2 IncreaseHydro · 4.4 MW · built
- Gulf Island Unit 1 IncreaseHydro · 1.0 MW · built
- Battery StorageBattery storage · 200 MW · withdrawn
- SolarSolar · 40.0 MW · withdrawn
- SolarSolar · 15.0 MW · withdrawn
- SolarSolar · 15.0 MW · withdrawn
- SolarSolar · 10.0 MW · withdrawn
- Solar and BatterySolar + storage · 7.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem