🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Maine

SOLAR + STORAGE · ISO-NE

Solar and Battery

Solar and Battery is a 7.5 MW solar + storage request withdrawn in the ISO-NE interconnection queue, in Androscoggin County, Maine.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2019 (completed)
  2. Withdrawn / abandonedOct 2019 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
917
Grid region
ISO-NE (New England)
Connection point (POI)
CMP Great Falls substation, Circuit 436D6
Location
Androscoggin County, Maine
Technology
Solar: 7.5 MW · Battery
Total requested
7.5 MW
Queue status
Withdrawn
Entered queue
29 August 2019
Proposed online date
December 2020
Withdrawn
October 2019

Location

Marker shows the centre of Androscoggin County; the queue data does not give exact sites.

Power plants in Maine · Transmission lines in Maine

Other requests in Androscoggin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem