United States › Grid › Interconnection queues › Maine
HYDRO · ISO-NEGulf Island Unit 2 Increase
Gulf Island Unit 2 Increase is a 4.4 MW hydro request built and operating in the ISO-NE interconnection queue, in Androscoggin County, Maine.
Request details
- Queue ID
- 351
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- CMP Gulf Island 115 kV
- Location
- Androscoggin County, Maine
- Technology
- Hydro: 4.4 MW
- Total requested
- 4.4 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 3 December 2010
- Agreement signed
- 14 February 2014
- Proposed online date
- April 2011
Location
Marker shows the centre of Androscoggin County; the queue data does not give exact sites.
Other requests in Androscoggin County
- Green Apple SolarSolar · 179 MW · agreement signed
- BD Solar Church HillSolar · 20.0 MW · agreement signed
- Turner Meadow SolarSolar · 19.8 MW · agreement signed
- Riley-Jay-Otis-LivermoreHydro · 28.3 MW · built
- SolarSolar · 20.0 MW · built
- Gulf Island Unit 1 IncreaseHydro · 1.0 MW · built
- Battery StorageBattery storage · 200 MW · withdrawn
- SolarSolar · 40.0 MW · withdrawn
- SolarSolar · 15.0 MW · withdrawn
- SolarSolar · 15.0 MW · withdrawn
- SolarSolar · 10.0 MW · withdrawn
- Solar and BatterySolar + storage · 7.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem