United States › Grid › Interconnection queues › Massachusetts

OFFSHORE WIND · ISO-NE

Vineyard Offshore Wind

Vineyard Offshore Wind is a 800 MW offshore wind request with a signed interconnection agreement in the ISO-NE interconnection queue.

Queue statusConsented
  1. PlanningQueued Nov 2016 (completed)
  2. ConsentedDec 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
624
Grid region
ISO-NE (New England)
Connection point (POI)
115 kV Barnstable Substation
Location
Massachusetts
Technology
Offshore Wind: 800 MW
Total requested
800 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
8 November 2016
Agreement signed
5 December 2025
Proposed online date
February 2026

Location

No county location in the queue data.

Power plants in Massachusetts · Transmission lines in Massachusetts

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem