OFFSHORE WIND · ISO-NEVineyard Offshore Wind
Vineyard Offshore Wind is a 800 MW offshore wind request with a signed interconnection agreement in the ISO-NE interconnection queue.
Queue statusConsented
- PlanningQueued Nov 2016 (completed)
- ConsentedDec 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 624
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- 115 kV Barnstable Substation
- Location
- Massachusetts
- Technology
- Offshore Wind: 800 MW
- Total requested
- 800 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 8 November 2016
- Agreement signed
- 5 December 2025
- Proposed online date
- February 2026
Location
No county location in the queue data.
Power plants in Massachusetts · Transmission lines in Massachusetts
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem