United States › Grid › Interconnection queues › Connecticut
BATTERY STORAGE · ISO-NEBattery Storage
Battery Storage is a 142 MW battery storage request with a signed interconnection agreement in the ISO-NE interconnection queue, in Litchfield County, Connecticut.
Queue statusConsented
- PlanningQueued Oct 2022 (completed)
- ConsentedSep 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Apr 2029 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1319
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- 115 kV line between Rocky River and Bulls Bridge substations
- Location
- Litchfield County, Connecticut
- Technology
- Battery: 142 MW
- Total requested
- 142 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 7 October 2022
- Agreement signed
- 15 September 2025
- Proposed online date
- April 2029
Location
No county location in the queue data.
Power plants in Connecticut · Transmission lines in Connecticut
Other requests in Litchfield County
- Kimberly Clark-Unit 1Gas · 28.0 MW · built
- SolarSolar · 19.8 MW · built
- Combined CycleGas · 550 MW · withdrawn
- Battery StorageBattery storage · 142 MW · withdrawn
- Battery StorageBattery storage · 45.3 MW · withdrawn
- BiomassOther · 42.0 MW · withdrawn
- Gas TurbineGas · 39.0 MW · withdrawn
- Biomass ProjectOther · 26.0 MW · withdrawn
- SolarSolar · 20.0 MW · withdrawn
- WindOnshore wind · 3.8 MW · withdrawn
- EE CT DER Group StudySolar · 3.7 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem