ONSHORE WIND Β· ISO-NE

Wind

Wind is a 3.8 MW onshore wind request withdrawn in the ISO-NE interconnection queue, in Litchfield County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2020 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
982
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource Canton 5R
Location
Litchfield County, Connecticut
Technology
Wind: 3.8 MW
Total requested
3.8 MW
Queue status
Withdrawn
Entered queue
30 March 2020
Proposed online date
September 2024

Location

No county location in the queue data.

Power plants in Connecticut Β· Transmission lines in Connecticut

Other requests in Litchfield County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem