United States › Grid › Interconnection queues › Connecticut
BATTERY STORAGE · ISO-NEBattery Storage
Battery Storage is a 45.3 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Litchfield County, Connecticut.
Queue statusWithdrawn / abandoned
- PlanningQueued Jun 2024 (completed)
- Withdrawn / abandonedAug 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 1562
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Eversource 115 kV Line from Frost Bridge #8R to Carmel Hill #11S
- Location
- Litchfield County, Connecticut
- Technology
- Battery: 45.3 MW
- Total requested
- 45.3 MW
- Service type
- Network resource (NRIS)
- Queue status
- Withdrawn
- Entered queue
- 7 June 2024
- Proposed online date
- June 2027
- Withdrawn
- August 2024
Location
No county location in the queue data.
Power plants in Connecticut · Transmission lines in Connecticut
Other requests in Litchfield County
- Battery StorageBattery storage · 142 MW · agreement signed
- Kimberly Clark-Unit 1Gas · 28.0 MW · built
- SolarSolar · 19.8 MW · built
- Combined CycleGas · 550 MW · withdrawn
- Battery StorageBattery storage · 142 MW · withdrawn
- BiomassOther · 42.0 MW · withdrawn
- Gas TurbineGas · 39.0 MW · withdrawn
- Biomass ProjectOther · 26.0 MW · withdrawn
- SolarSolar · 20.0 MW · withdrawn
- WindOnshore wind · 3.8 MW · withdrawn
- EE CT DER Group StudySolar · 3.7 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem