🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Connecticut

BATTERY STORAGE · ISO-NE

Naugatuck Avenue Battery Storage

Naugatuck Avenue Battery Storage is a 205 MW battery storage request with a signed interconnection agreement in the ISO-NE interconnection queue, in New Haven County, Connecticut.

Queue statusConsented
  1. PlanningQueued Jan 2021 (completed)
  2. ConsentedOct 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1089
Grid region
ISO-NE (New England)
Connection point (POI)
Devon 115 kV open position between 4T and 5T
Location
New Haven County, Connecticut
Technology
Battery: 205 MW
Total requested
205 MW
Service type
Energy only (ERIS)
Study phase
Executed
Queue status
Active
Entered queue
8 January 2021
Agreement signed
3 October 2023
Proposed online date
May 2027

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New Haven County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem