United States › Grid › Interconnection queues › Connecticut
BATTERY STORAGE · ISO-NENaugatuck Avenue Battery Storage
Naugatuck Avenue Battery Storage is a 205 MW battery storage request with a signed interconnection agreement in the ISO-NE interconnection queue, in New Haven County, Connecticut.
Queue statusConsented
- PlanningQueued Jan 2021 (completed)
- ConsentedOct 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget May 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1089
- Grid region
- ISO-NE (New England)
- Connection point (POI)
- Devon 115 kV open position between 4T and 5T
- Location
- New Haven County, Connecticut
- Technology
- Battery: 205 MW
- Total requested
- 205 MW
- Service type
- Energy only (ERIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 8 January 2021
- Agreement signed
- 3 October 2023
- Proposed online date
- May 2027
Location
No county location in the queue data.
Power plants in Connecticut · Transmission lines in Connecticut
Other requests in New Haven County
- CPV Towantic Energy CenterGas · 745 MW · built
- Wallingford GT UprateGas · 350 MW · built
- New Haven Harbor 2-4Gas · 130 MW · built
- Wallingford Energy CenterGas · 100 MW · built
- A. L. PierceGas · 99.6 MW · built
- Waterbury Generating FacilityGas · 95.7 MW · built
- CPV Towantic IncreaseGas · 55.5 MW · built
- CPV Towantic incrementalGas · 45.0 MW · built
- Devon 10Other · 20.0 MW · built
- Milford Upgrades - Phase IGas · 16.6 MW · built
- Wallingford SolarSolar · 15.0 MW · built
- Fuel CellGas · 14.4 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem