United States › Grid › Interconnection queues › Connecticut

GAS · ISO-NE

CPV Towantic incremental

CPV Towantic incremental is a 45.0 MW gas request built and operating in the ISO-NE interconnection queue, in New Haven County, Connecticut.

Queue statusOperating
  1. PlanningQueued Sep 2018 (completed)
  2. ConsentedFeb 2020 (completed)
  3. Construction (completed)
  4. OperatingTarget Mar 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
784
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource 115 KV lines 1575, 1585 and 1990
Location
New Haven County, Connecticut
Technology
Gas: 45.0 MW · Oil
Total requested
45.0 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
18 September 2018
Agreement signed
26 February 2020
Proposed online date
March 2020

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New Haven County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem