United States › Grid › Interconnection queues › Connecticut

GAS · ISO-NE

CPV Towantic Energy Center

CPV Towantic Energy Center is a 745 MW gas request built and operating in the ISO-NE interconnection queue, in New Haven County, Connecticut.

Queue statusOperating
  1. PlanningQueued Dec 2011 (completed)
  2. ConsentedNov 2015 (completed)
  3. Construction (completed)
  4. OperatingTarget May 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
384
Grid region
ISO-NE (New England)
Connection point (POI)
CL&P 115 kV
Location
New Haven County, Connecticut
Technology
Gas: 745 MW · Oil
Total requested
745 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Operational
Entered queue
29 December 2011
Agreement signed
1 November 2015
Proposed online date
May 2018

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New Haven County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem